Planning basis
A specified input, scope or configuration not yet demonstrated in operation.
Capacity, recovery and financial confidence require different evidence. The experience makes their connection visible.
An equipment name defines a design candidate. Representative-feed tests and complete-cycle evidence establish accepted performance.
| Control | Current planning basis | Acceptance boundary |
|---|---|---|
| Gravity banks | 23 dry t/h per active C1000 | Recovery and mass pull must be demonstrated on qualified feed. |
| Tailings presses | 25 duty plus one reserve | Complete cycle≤74.63 min;90 min case needs 31 duty plus reserve or derating. |
| Grinding | 14 duty plus reserve at Wi16 | Wi20 requires 17 duty plus reserve at 150 kW boundary or supported derating. |
| Electrical | Nine proposed XQ1140 modules | Running-load and starting study remains open. |
Site rights, permits, drainage, support, traffic and utilities are specific to the actual destination.
| Control | Current planning basis | Acceptance boundary |
|---|---|---|
| Footprint | 4.95-acre core;7.573457-acre secured example | Representative arrangement, not surveyed deployed footprint. |
| Containment | Defined liners, berms and liquid duties | Actual catchments, usable volume, collection rates and states require acceptance. |
| Water | 20.491m³/h process makeup | Initial fill, ancillary and nonproductive demand are additional. |
| Mobility | Trailers, frames, mats and supports | Road, lift, mass, axle and clearance qualification remains required. |
Separate preparation, hot-assay and clean-analysis rooms support source-to-shipment traceability.
| Control | Current planning basis | Acceptance boundary |
|---|---|---|
| Source qualification | Representative material and assays | No measured feedstock results are proven by the images. |
| Routine feed | One composite per 150 dry tonnes | Sampling must address variability, partial lots and QA/QC. |
| Analytical controls | 25% QA workload allowance | Peak method mix, turnaround and reserves require verification. |
| Shipment release | Weight, moisture, assays, seals and splits | Buyer and umpire procedures need actual agreement. |
The live site should explain what management plans to measure and how a lender can inspect the record.
| Control | Current planning basis | Acceptance boundary |
|---|---|---|
| Daily reconciliation | Feed, concentrate, cake, water and cash | Internal recycle is not new feed or sales. |
| Physical security | 388 devices/payloads per pilot planned | Not an installed count or creditor-security evidence. |
| Staffing | 48 core FTE per pilot | 29 nonsecurity plus 19 security; not occupancy or actual hires. |
| Funding controls | Daily liquidity and closeout retention | Final covenants, reserves and reporting require documents. |
Sample custody, analytical QA, dry-tonne records, process performance, shipment identity and settlement each support the cash-producing chain.
The same status travels with a claim into pages, exhibits and investor communications.
A specified input, scope or configuration not yet demonstrated in operation.
A named assay, trial, approval, contract or engineering release record.
Publish only after verification, with date, scope and responsible reviewer.
A measured period result with method and reconciliation, distinct from forecast.
The supplied documents establish a detailed planning record. They do not establish an operating plant, completed permits, secured feedstock or demonstrated recoveries. Evidence boundary →
Review technical conditions alongside the model and the proposed funding sequence.
Request investor access → Review the debt program →Eligibility, investment terms and commitments are established through approved offering documents and diligence. Forecasts are conditional. Repayment is not guaranteed.