Five independently operable plants

Repeat the system.
Keep operations accountable.

The proposed portfolio separates equipment, operating records and campaign timing while retaining common process standards.

Execution Team

A dedicated team for every pilot.

Each pilot is planned around a 48-person core, supported by shared corporate specialists, qualified relief and external experts. Mike Iannacchione will handpick the five senior pilot general managers. Explore each team’s responsibilities, qualifications and operating interfaces.

Pilot 1

Establish the operating standard through disciplined commissioning, reliable records and demonstrated performance. Transfer accepted lessons through controlled procedures and training.

Meet the Pilot 1 team model →

Pilot 2

Apply accepted learning while independently qualifying the site, source material, equipment readiness and people. Replication retains each pilot’s own release requirements.

Meet the Pilot 2 team model →

Pilot 3

Maintain operational depth as the portfolio grows, with attention to specialist availability, maintenance coverage, laboratory continuity and coordinated logistics.

Meet the Pilot 3 team model →

Pilot 4

Coordinate concurrent operations and campaign moves while protecting each site’s essential people, critical spares, safe work and maintenance commitments.

Meet the Pilot 4 team model →

Pilot 5

Prepare the latest pilot for production and the common Month 60 commercial boundary, including final shipments, settlement and site-release duties.

Meet the Pilot 5 team model →
Explore leadership, advisers and recruiting →
pilots-architecture
GVP 01 — GVP 01 | Approved plant aerial showing terrain, source deposits, roads, gates, security, receiving, inline haul scale and cake-loading spine. North is at the top and east at the right. The dimensioned register governs the 162-position planning inventory. AI-generated planning illustration.
Planned facility visualization
GVP01 /40 · One representative planning arrangement, reused to explain five proposed pilots. Image basis →
01

Dedicated

Each plant carries ordinary process equipment, laboratory, water inventory, control and security functions.

02

Repeatable

A common architecture supports comparable procedures, performance measurement and maintenance.

03

Separately controlled

Site identity, lot records, production, inventories and commissioning remain distinct.

Five-pilot design basis →
pilots-schedule
Staged deployment

One pilot at each funding round.

M1 is February 2027. Introductions at M1/M7/M13/M19/M25 are conditioned on funding, site readiness and technical acceptance. Launch begins startup; it does not mean a producing plant.

Matched funding and pilot timeline

Sand=startup and ramp · Green=modeled full-rate interval · Gray=remaining lifecycle cash. The chart shows planned stages, not verified operations.

Pilot 1Full M12Pilot 2Full M18Pilot 3Full M24Pilot 4Full M30Pilot 5Full M36M1M12M24M36M48M54M60
Matched pilot deployment and lifecycle schedule
PilotFunding / launch30% ramp / first feed70% rampFull-rate startStop periodLast lifecycle cash period
P1R1 / M1M10M11M12M56M60
P2R2 / M7M16M17M18M58M60
P3R3 / M13M22M23M24M60M60
P4R4 / M19M28M29M30M60M60
P5R5 / M25M34M35M36M60M60

First feed is project M10/16/22/28/34 and full-rate starts are M12/18/24/30/36. Production ends are M56/M58/M60/M60/M60, with the final commercial boundary at M60,31 January 2032. Principal maturity is elapsed M36/42/48/54/54; participation rights may continue after principal maturity until capped, subject to actual cash.Schedule basis →

pilots-diversification
A precise diversification claim

Spread plant-level exposure.
Understand shared dependencies.

Five physical pilots create separate operating campaigns. If earlier launches achieve their milestones, later investors can examine more operating evidence. That does not establish statistical independence, legal ring-fencing, secured feedstock or a guaranteed or exponential decline in risk.

Portfolio claim boundary →

Separate by design

  • Process trains and laboratories
  • Campaign dates and lot identities
  • Operating records and custody
  • Routine equipment and inventories

Shared across the program

  • Recovery and grade assumptions
  • Finance and commercial mechanisms
  • Vendors, utilities and Nevada exposures
  • One specialist terrain capability
pilots-mobility
RA 06 — RA 06 | GSE equipment concept adapted with GVP operator branding; contractor support equipment. AI-generated planning illustration.
Planned facility visualization
RA06 · Shared terrain crane concept; not an owned-fleet record. Image basis →
Mobilize deliberately

Move to the material
when the destination is ready.

Reinforced frames and container-sized bodies use reusable supports and prepared sites. The four-day move and seven-day advance objectives need demonstrated transport, ground, installation and operating readiness.

Specialist terrain equipment is shared under a one-at-a-time planning assumption. Availability must cover setup, recurring support and demobilization.

Mobility and terrain basis →
pilots-close
Your next step

Inspect the plan at the level of each plant.

Connect the repeatable architecture with qualified material, actual site readiness and committed capital.